FG Targets 2031 Completion for Trans-Sahara Highway

Trans-Sahara Superhighway project under construction across Nigeria

The Federal Government has set 2031 as the target for completing key sections of Nigeria’s Trans-Sahara Superhighway, with the project expected to improve connectivity, agricultural logistics, commerce and security across communities in the South-East and North-Central regions.

/ You Might Also Like /

Minister of Works, David Umahi, disclosed the target during an inspection of ongoing construction on Section Two of the highway in Ado Local Government Area of Benue State. According to a report by the News Agency of Nigeria (NAN), Umahi said the projects could be completed by 2031, subject to continuity in implementation.

The latest project configuration places Section One at approximately 123 kilometres from Ebonyi State to the Ebonyi-Benue boundary, while Section Two covers about 173.4 kilometres through Benue, Enugu and adjoining areas. Together, the two sections span almost 300 kilometres.

Nearly 300 Kilometres Covered by Two Sections

Section One runs from the Ebonyi axis to the Ebonyi-Benue boundary and is currently designed as a single carriageway. The Federal Government has indicated plans for a second carriageway to align the project with other major infrastructure initiatives.

Section Two extends approximately 173.4 kilometres from the end of Section One through Benue and Enugu towards adjoining states and the Benue River-Nasarawa boundary. The route remains subject to design adjustments as construction progresses.

Umahi said the combined sections would significantly improve access between communities and states along the corridor. The minister also identified the 8.9-kilometre Afikpo bypass in Ebonyi State as part of the infrastructure interventions associated with the corridor. The bypass is currently being dualised.

The minister said the completed road would have a design speed of 100 kilometres per hour, which could substantially reduce journey times along the affected routes.

Government Links Highway to Agriculture and Commerce

The Federal Government expects the highway to strengthen economic activity by improving the movement of agricultural products from major farming communities to markets.

Benue, Ebonyi and Enugu are important agricultural-producing areas, and improved road infrastructure could reduce the logistical difficulties associated with moving farm produce between production centres and major consumption markets.

Umahi said better connectivity would bring communities closer to markets and improve commercial activity across the corridor. He also linked the project to improved security, arguing that better roads would enable security personnel to reach previously isolated communities more efficiently.

The wider Trans-Sahara Highway has a much broader regional significance. The African Development Bank identifies the corridor as a major African integration project connecting Algeria, Tunisia, Mali, Niger, Chad and Nigeria. The bank says the wider Trans-Sahara Highway spans more than 9,000 kilometres and forms part of the continent's efforts to improve regional trade and connectivity.

Property Impact Becomes Part of Project Planning

The latest inspection also highlighted the impact of highway construction on properties and communities along the alignment.

Umahi directed contractors to minimise unnecessary demolition of houses and other structures. Project officials said design reviews were being undertaken to adjust sections of the alignment and replace selected culverts with bridges where necessary to reduce the impact on private properties.

The minister also appealed to affected communities to cooperate with enumeration and valuation teams involved in the project. He said property owners with valid claims would receive compensation where required.

For the housing and real estate sector, the issue is significant because major transport corridors can alter land-use patterns and property values. Improved accessibility can increase the development potential of previously underserved areas, but infrastructure expansion can also create displacement and compensation challenges where existing settlements fall within road alignments.

Effective planning will therefore remain important as the project progresses, particularly in communities where residential, agricultural and commercial properties intersect with the highway corridor.

Funding Remains a Major Constraint

Despite the 2031 target, the Federal Government acknowledges that funding remains one of the biggest challenges facing the project.

Umahi said the government does not have enough resources to execute all road projects simultaneously, meaning implementation will depend partly on the availability of funds.

The government has previously explored alternative financing for the Trans-Sahara Highway. In 2024, the Works Ministry opened discussions with the African Development Bank on securing financing for important sections of the Trans-Sahara and Coastal Highways. The discussions formed part of efforts to mobilise additional resources for major transport infrastructure projects.

The financing question remains particularly important because the Trans-Sahara Highway forms part of a much larger regional transport network. The African Development Bank has described the broader corridor as an important route for regional integration and trade between North, West and Central Africa.

Project Scope Has Changed

The highway project has undergone changes in scope and cost during its development.

Nairametrics reported that the Ebonyi-Benue section was revised in 2025 from an earlier 118-kilometre scope to 221.64 kilometres because of poor soil conditions. The revision included two additional bridges and increased the contract value from N361 billion to N445.851 billion.

The latest project update, however, places Section One at approximately 123 kilometres. This difference reflects changes in project configuration and scope as engineering work has progressed.

Such revisions highlight the technical and financial complexity involved in delivering large-scale road infrastructure across areas with varying terrain, soil conditions and settlement patterns.

Connectivity Could Influence Development Along the Corridor

For Nigeria's housing and property market, the long-term significance of the project extends beyond the highway itself.

Transport infrastructure can improve access to land, reduce travel times and make locations outside established urban centres more attractive for residential, commercial and industrial development. Better connectivity can also support the expansion of economic activity into areas that previously faced poor access to major markets.

However, infrastructure-led property growth depends on more than road construction. Reliable electricity, water supply, drainage, security, telecommunications and effective land administration will also determine whether improved connectivity translates into sustainable urban and housing development.

The Trans-Sahara corridor could therefore create opportunities for new settlements and economic centres, particularly where state and local authorities coordinate transport planning with land-use and housing policies.

Wider Regional Importance

The Nigerian section forms part of the wider Trans-Sahara Highway, a continental corridor designed to connect Lagos with North Africa.

The African Development Bank describes the highway as a strategic trans-African route linking six countries and supporting regional integration. Its broader objective includes reducing transport and logistics costs, improving accessibility and supporting trade across the participating countries.

Progress on Nigeria's sections therefore has implications beyond domestic transportation. Improved links could strengthen the movement of goods between Nigerian markets and neighbouring countries while supporting wider African trade integration.

The bank has also documented economic benefits from completed sections of the corridor in other countries, including reduced travel times and increased economic opportunities for communities along the route.

2031 Target Will Depend on Funding and Continuity

The Federal Government's 2031 target provides a clear timeframe for the completion of the ongoing sections, but achieving it will depend on sustained financing, construction continuity and effective management of community and property issues.

The government will also need to maintain consistent project funding as construction advances while managing design changes, compensation obligations and additional infrastructure requirements.

For communities and businesses along the corridor, successful completion could bring improved access to markets, lower transport barriers and new development opportunities. For investors and policymakers, the project represents a potentially important infrastructure corridor whose economic value will depend on the quality and continuity of its execution.

If delivered as planned, the Trans-Sahara Superhighway could become an important transport and economic link connecting communities across several Nigerian states while contributing to the country's broader regional trade ambitions.

READ MORE

Ayomide Fiyinfunoluwa

Written by Ayomide Fiyinfunoluwa, Housing Journalist & Daily News Reporter

Ayomide is a dedicated Housing Journalist at Nigeria Housing Market, where he leads the platform's daily news coverage. A graduate of Mass Communication and Journalism from Lagos State University (LASU), Ayomide applies his foundational training from one of Nigeria’s most prestigious media schools to the fast-paced world of property development. He specializes in reporting the high-frequency events that shape the Nigerian residential and commercial sectors, ensuring every story is anchored in journalistic integrity and professional accuracy.

connect on linkedin

https://www.nigeriahousingmarket.com/author/ayomide-fiyinfunoluwa
Previous
Previous

Shettima Demands Stronger Accountability for $500m Agriculture Programme

Next
Next

Nigeria Targets Emerging Market Status After FTSE Frontier Market Upgrade